Construction daily report template: what to fill in, with an example

The fields a construction daily report needs, a filled-in example and a blank template to print.

Updated on 11/02/2026

The construction daily report — also called the daily log — records what happened on site each working day: who was there, what was done, what the weather was like and what went wrong. Kept properly, it settles deadline disputes with the client, backs up progress claims and tells the project's story to anyone who was not there.

The fields you cannot skip

FieldWhat to writeWhy it matters
Project and dateProject name or number, date and day of the week.Without a date, the record proves nothing.
WeatherMorning and afternoon separately: clear, cloudy, rain, heavy rain.Rain is the most common reason for delays — and the most disputed one.
Working conditionWorkable, partly workable or unworkable.It turns "it rained" into "lost day" when the deadline is discussed.
CrewHow many people, which trade (mason, laborer, electrician) and how many hours.Shows whether the site has enough people for the schedule.
EquipmentMixer, scaffolding, truck, machinery — what was used that day.Helps check equipment rental and daily rates.
Work performedThe task and where: "poured the 2nd-floor slab, grid lines A to C".It is the basis for progress measurement and the schedule.
IncidentsMissing material, accidents, inspection visits, client requests, rework.If it is not written down, it did not happen — in a future dispute.
PhotosOf the day's work, with captions.A photo beats a paragraph when someone doubts you.
SignaturesFrom whoever recorded it and from the engineer of record or inspector.Without signatures it is just a note.

Example of a filled-in daily report

ProjectGarden Residences — No. 014
DateTuesday, October 14
WeatherMorning: clear · Afternoon: rain
ConditionPartly workable (rain from 2 p.m.)
Crew1 site foreman (8h) · 4 masons (8h) · 3 laborers (8h) · 1 rebar fixer (6h) — total: 9 people
Equipment400 L concrete mixer · facade scaffolding (12 m)
Work performedRebar for the 2nd-floor beams (grid lines A to C). Masonry on the 1st floor, walls 4 to 9. External masonry stopped at 2 p.m. due to rain.
IncidentsDelivery of 40 bags of cement was 2 hours late. Client visited the site at 10 a.m. and asked for a quote for a barbecue area.
Photos6 photos (beam rebar, masonry, cement delivery)
SignaturesSite foreman · Engineer of record

Notice that the example says where each task was done and at what time the rain stopped work. That detail is what makes the log worth something three months later.

Blank template to print

Print it and keep a clipboard with sheets on site. One sheet per working day.

CONSTRUCTION DAILY REPORTNo. ______
Project
Date
____/____/______   Day of the week: ____________
Weather
Morning: ( ) clear ( ) cloudy ( ) rain  ·  Afternoon: ( ) clear ( ) cloudy ( ) rain
Condition
( ) workable   ( ) partly workable   ( ) unworkable
Crew (trade, qty., hours)
Equipment
Work performed
Incidents
Photos (no. and subject)
Recorded by
Engineer of record

Mistakes that make a daily log worthless

  • Filling it in at the end of the week, from memory. The log belongs to the day. Written later, nobody trusts it — not even you.
  • "General work". Generic activities measure nothing. Name the task and the place.
  • Hiding problems. Missing material, rain that stopped work, client requests outside the contract: that is exactly what you will need to prove later.
  • No signatures. Without the recorder's and the engineer's signatures, the log is just an opinion.
  • Sheets that disappear. Paper gets wet, torn or left in someone's truck. Keep a copy — or record it straight on your phone.

Depending on the contract and the type of project, a daily log may be required by the client, the public owner or local regulations. Check what applies to your project.

Paper or phone?

Paper works, but it has hidden costs: someone has to type it up, photos stay on each person's phone and the client calls to ask "how is the project going?". On a phone, the daily log is done on the spot with photos, signed with a finger, the client follows it on a portal and the lost-days report comes out by itself. For the step-by-step of filling it in, see how to write a daily report.